Monday, 14 November 2011

Week 14 - Monday update

Good start to the day, there were 5 lads on site before 8am! Mike the plasterer, Stan and Robbie the roofers, Keith and Johnny, 2 more plasterers. Simon and Alex will also be around today.

It should be a pretty busy week this week with all that's going on:

Mon/Tues the windows should arrive and get put in. (Simon & Alex)

Plastering front bedroom and hallway (Keith & Johnny)

Ridge tiles and pointing on the roof finished off (Stan and Robbie)

Mon - finishing off skimming in the kitchen and maybe boarding out some of the other areas (utility and sun room - Mike).

Next Wed, we have the kitchen fitter (Trevor Kettlewell) coming to get his measurements so he can go off and build the kitchen. We hope to have that fitted the week before Xmas.

Thurs, screed goes down to level the whole area (kitchen, utility, sun room, lounge)

Updates to follow during the week...