Tuesday, 1 November 2011

Week 12 roof work




Sent from my iPadI took the day off work yesterday to try and get things back on track a little. There were loads of tiles to move from the front of the house so the skip could get removed and a new one put in its place. Then Simon and I cleared out a load of rubble from the kitchen and new utility room, so the sparkies can crack on today. Progress on the roof was good yesterday; the skylights have gone in and the woodwork is almost in place for the tiles. Hopefully, we're on track for having the roof done by the end of the week. might be taking Thursday off as well, to insulate the kitchen and utility.

No comments: