No piccies this week as I've been getting home when it's dark. Progress is being made though. The roof should finally be finished by tomorrow. The plaster arrived this morning to board out the kitchen, sun room and utility. He should be finished by Mon next week and will have to return to do the lounge. Alex has been doing the joinery to allow the plasterers to board the steel transition from the kitchen to the sun room and lounge, he's also been bricking up any areas which need to be done. The sparkies have done their 1st fix and got everything in place. Tomorrow, the scaffolding comes down too, so Alex can get the windows in next week.
Next week
Mon/Tues the windowns should arrive and get put in.
Next Wed, we have the kitchen fitter coming to get his measurements so he can go off and build the kitchen. We hope to have that fitted the week before Xmas.
Thurs, screed goes down to level the whole area (kitchen, utility, sun room, lounge)