Soil pipe from the upstairs toilet has been re-routed and attached now. It comes down through the roof space and into the bathroom, where it will be hidden by the new boiler cupboard. Thankfully, we don't have to pee in a bucket during the night anymore.

The windows in the kitchen have been taken out and bricked up.

The existing utility outside bricks have been knocked in and the lower level of the new wall has been built.

The kitchen extension has breeze blocks on on side built up to about head height, with the second layer of bricks starting to be built around the base engineering bricks.

The sparks have also been here working on setting new points into the wall and connecting some bits in the new fuse box.

Aim by the end of this week is to have the brickwork built and ready for the steels to come next week. Minster engineering are coming to measure up on Friday.