Monday, 30 January 2012

End of January update

Been a few weeks since the last post, so thought I would update the blog. In between posts I have been to Zambia with work and Anne is now 31 weeks gone.

Most recent events involve the kitchen installation, and final work with electrics and plumbing. Kitchen is getting painted today and Andy should be completing much of the remaining plumbing work.

Outstanding jobs are:
2nd fix electrics in dining room and family room
2nd fix plumbing for bath upstairs and family room/dining room rads
carpeting entrance hall, baby's room, lounge, hall stairs and landing,
kitchen flooring
lino in bathrooms
final coats of calico in baby's room, family room and dining room
guest bedroom to be re-decorated
outside area to be re-gravelled

Jane and Ed helped this weekend with the painting. Jane was mainly looking after the hall stairs and landing, I concentrated on family room and dining room and Anne was woodwork. Ed helped here and there with odd jobs like sanding, hoovering, insulating, inbetween dealing with the children, which was really useful.

Next weekend we have the remaining coats of natural calico to get sorted in the dining room,lounge and the baby's room.

On Monday 6th Feb, we have the carpets getting fitted and I think we can then start bringing our posessions out of hibernation and back into the house from the garage. That will be a milestone in the whole project, as we start to re-claim the house and make it home again.

Mid-Feb is still looking like the target for internal jobs to be done, we then have silly things like getting the decking down outside, cleaning UPVC outside etc. They're all small-fry in comparison though.

Snug





Family room





Bay window in dining room





Stairs





Dining room 2 coats of white on





Utility room





Kitchen fitting 3





Kitchen fitting 2





Kitchen fitting





Monday, 9 January 2012

Lounge, temporary setup





Kitchen walls all painted, as of yesterday





Temporary kitchen





Temporary setup in sunroom and kitchen





Ben having breakfast





Dining room, stripped





Upstairs shower complete





Upstairs shower being built





Family room stripped





Family room, emptied





Post Xmas & NY Update

It's been a while! Last post was 20th December I think. Ben was evacuated to his Gran's the week before Christmas, to ease the pressure on us and allow us to get on with things. We managed to get a lot of work done in the week up to Christmas; working until Xmas eve and resuming on the Thu after Christmas.

We had convinced ourselves not to bother with e dining room and family room, but when we moved things over to the new are of the house, Anne got a second wind and convinced us that it was worth dealing with the mess all in one go, rather than waiting another 18 months and resuming.

So, as things stand:
Kitchen - elec fix (apart from cooker hood), painted and waiting for units installation on w/c 23rd Jan. Flooring to be re-laid
Lounge - elec fix, painted and waiting for carpet
Sun room - elec fix, needs one more white coat, waiting for flooring.
Our bedroom - done, we're sleeping in it now. Just needs final furniture and dressing.
Baby's room - elec fix, needs 2 x coats of calico
Hallway - elec fix, painted but needs carpet down and dressing.
Bathroom - elec fix, painted, shower in, all plumbed. Waiting for flooring and needs dressing.

Dining room & family room: stripped, sanded 1st fix elecs done, rads off. Needs skimming this week and painting w/c 23rd, then 2nd fix elecs.

Hall, stairs and landing: sanded, needs sugar soaping and painting.

Upstairs bathroom: elec fix, painted. Shower not draining properly, so needs a look at. Sinks and toilet are all plumbed in and tiling done. Bath needs fitting and flooring needs to go down.

Balcony bedroom: wet spot on ceiling needs investigating, remove dado rails, sand down, sugar soap and paint. Then flooring and re-dress as guest room, which G&g seem to be very excited about.

Well, that should keep us busy until the middle of Feb. Oh, I almost forgot, the baby is 28 weeks old now and growing! Off to Zambia next week with work and back on 23rd and midnight.

Pictures to follow...