Tuesday, 20 December 2011
Upstairs bathroom, painted
Monday, 19 December 2011
A week later
Bathrooms upstairs and down are being fitted. the tiler was here over the weekend and so was Alex, fitting the shower panels. Today Andy has been fitting the sinks and taps upstairs and down. Tomorrow, I will be painting the upstairs bathroom.
Ben has been shipped off to his Gran's for the week to give Anne and I a chance to crack on. The poor boy was being neglected here and we were struggling to get much done. Jenny has been our saviour this week. What would we do without her?
Photos to come..l
Monday, 12 December 2011
Utility room - done!
Sunday, 11 December 2011
Weekend shift over
Saturday, 10 December 2011
Weekend work update
This week the sparkles will second fix, Alex will be sorting the upstairs bathroom out, the plasterers will be coming to do the downstairs and upstairs bathrooms and Andy the plumber will be finishing his stuff off. We're hoping to have at least a temporary kitchen for Christmas.
Wednesday, 7 December 2011
Week 17 - midweek report
My job has been concentrating on getting the kitchen whited out. So far I've done 3 coats on the ceiling and 2 on the walls. I am hint that the ceiling will be ok now and that I'll just have to give the walls one more, but I'll see in the morning.
The lads from hotbox have been on site all day and the stove in nearly installed and the flu sprayed.
Alex h been working on bits and bobs, mainly upstairs. The skylight is now in the bathroom and the room has been opened up into what was the storage area.
All in all, it feels like it has been a productive day.